| M11 Gorey to Enniscorthy PPP Motorway Official Opening ![]() The PPP contract was awarded to BAM PPP PGGM Iridium in October 2015. The design and construction activities were delivered by a joint venture between BAM Civil Ltd and Dragados Ireland Ltd. Costing €400 million, the combined 39 km of the M11 motorway and associated roads have been under construction since January 2016 and have been completed on schedule with 1,850,000 person-hours completed on-site during the construction period. The opening of the M11 Gorey to Enniscorthy PPP Scheme was officiated by An Taoiseach Leo Varadkar TD in the presence of Mr Cormac O'Rourke Chairman TII and Cllr. Michael Sheehan Cathaoirleach of Wexford County Council. The scheme includes fifty-seven new structures, including eight overbridges, five under bridges, thirty-one farm accommodation underpasses, and three Rail River bridges. write your comments about the article :: © 2019 Construction News :: home page |