| Premiere in the Baltics ![]() The new-build Tartu Bridge will be 400 m long overall and 15.5 m wide. Most of the formworking can be done on compacted riverbank subsoil with the load-bearing towers Staxo 100. The river itself cannot be dammed or even diverted however, so shoring over the full span is not an option. And so a high-performing Doka cantilever forming traveller debuted in a Baltic state to throw the 55-metre middle section of the bridge across the waters. The concreting sections are 5.1 m long. Doka formwork instructors were in attendance to coordinate setup and familiarise the site crew with the procedures. A formwork instructor was also on site for the cantilever forming traveller's first advance, to make sure that everything went smoothly. From the second concreting section on the site crew was well able to take charge of the advancing procedure without further assistance. The cantilever forming traveller will be on site for only a very short time, so the project owner benefits from the Doka Group's rental model. Instead of being bought outright, the formwork system is simply hired for the duration. Usage of the formwork system is billed by the day and the equipment is returned as soon as the job is done. Doka has a branch in Estonia, so formwork engineers were always on call to answer queries. Moreover, communication in the local language facilitated technical instruction for the entire construction crew. This major infrastructure project is scheduled for completion by the end of 2015. write your comments about the article :: © 2014 Construction News :: home page |