| Balfour Beatty Utility Solutions awarded offshore cabling contract Balfour Beatty Utility Solutions has been awarded the contract by E.ON to install the cable for its Humber Gateway offshore wind farm. The contract, worth circa £19 million, will involve the design and installation of a 30km section of underground 132kV cable which will be used to connect the Humber Gateway offshore wind farm to a new onshore substation at Hedon in East Yorkshire. E.ON's £736 million Humber Gateway wind farm, situated 8km off the Yorkshire Coast close to the mouth of the Humber Estuary, will consist of a 73 turbine array that will generate up to 219MW of electricity, enough energy to power up to 170,000 homes. Balfour Beatty will begin cabling work in summer and E.ON's entire Humber Gateway project is expected to be complete in Spring 2015. write your comments about the article :: © 2012 Construction News :: home page |