Finland's Poyry to modernize transmission system substations in Austria

Pöyry's Energy business group has been awarded contracts by the Austrian transmission system operator Austrian Power Grid AG, for the extension and modernisation of the Bisamberg, St. Peter and Zell/Ziller substations. The overall value for Pöyry amounts to approximately EUR 9.3 million, and it has been booked in the first quarter order stock.

The scope of the work comprises detailed design engineering, project management, construction and installation services as well as the supply of equipment. Dismantling of the existing equipment and installation of the new components will be realised stepwise in close cooperation with the client. The projects will start in March/April 2012. St. Peter and Zell/Ziller will be completed by the end of 2013, and Bisamberg by the end of 2014.