| Fluor to support Luminant's Sandow contract Fluor Corporation announced that it will provide construction and commissioning support to Luminant for a $100 million-plus contract for air quality control upgrades on its Sandow Plant Unit 4 electric station in Rockdale, Texas. The Sandow Steam Electric Station Unit 4 is a lignite-fueled generating unit owned and operated by Luminant. Fluor booked the full contract value in the first quarter of 2008. In addition to this new contract, Fluor has provided front-end design and detailed engineering for this selective catalytic reduction project. Engineering began in May 2007, with an estimated construction completion date of May 2010. Site mobilization occurred in January 2008, with the major tie-in outage scheduled for February to April 2010. write your comments about the article :: © 2008 Construction News :: home page |