Multiplex marks Wembley's progress

Multiplex advises that there has been no material change in construction status of the new Wembley Stadium from that reported on 1 August and 17 August 2006.

Works relating to the removal of temporary works and those such as commissioning and cleaning that are required to achieve practical completion are ongoing. These remaining works remain on programme and will complete prior to the date at which the stadium becomes operational.

There are a number of critical works and activities that are the responsibility of the Wembley National Stadium Ltd (WNSL). WNSL has not yet begun some of these works and others which WNSL has begun are not complete.

Multiplex further advises that the Court of Appeal has rejected Cleveland Bridge (UK) Limited's application for permission to appeal following the High Court's judgement in favour of Multiplex.