contacts
technologies

A modern approach to planning and work operations in industrial scaffolding construction

Press release

A modern approach to planning and work operations in industrial scaffolding construction

Construction of the new vitamin A plant at BASF in Ludwigshafen, Germany

In the industrial environment more than anywhere else, process and operational reliability requirements are particularly stringent. At BASF SE in Ludwigshafen, Germany, PERI has demonstrated that safety and cost-effectiveness can be combined with ease by making use of state-of-the-art, BIM-based scaffold planning and innovative systems.

The innovative BIM-based scaffolding concept used in the construction of the state-of-the-art acetylene plant in Ludwigshafen back in 2018 was the first joint project between BASF SE, promaintain and PERI. While this plant was being commissioned in stages, work was already beginning on the vitamin A complex. The new plant is expected to increase BASF's annual production capacity for vitamin A by 1, 500 t. Around 600 machines and devices as well as 5, 000 test points are being integrated into the process control system. In addition, 250 linear metres of pipe bridges had to be constructed.
Cross-trade BIM methodology

A joint project team led by promaintain Project Manager Tino Freund and PERI Project Manager Anita Rösch, planned and coordinated the wide-ranging industrial scaffolding tasks. As in previous projects, BIM methodology with cross-trade 3D planning, coordination and execution provided the basis for this. Processes were planned and documented in terms of scheduling and spatial requirements. All of the information was digitally retrievable: requirements data (locations, responsibilities), planning data, drawings, parts lists, static calculations, 3D models. Just like in a digital scaffolding book, the current status of each scaffolding unit could be selected and retrieved: requested, in planning, planned, under construction, completed, released, deregistered, dismantled. Collecting this data not only facilitates project controlling, but also simplifies accounting and evaluation processes. With this information, subsequent projects or recurring maintenance work can be optimised and then actioned even more efficiently in the future.

Competent engineering during construction is an essential aspect of a customised PERI scaffolding solution. For example, the on-site project team in Ludwigshafen registered and managed over 4, 000 scaffolding units using Autodesk's BIM 360 Field construction field management software over the course of the 18-month project term. And the majority of the total scaffolding quantity of around 2, 000 t was planned with CAD and made available as a 3D model. This enabled subsequent users to check the scaffolding plans for usability, variability and flexibility before they were erected and to have them optimised if necessary. This minimised conversion times, optimised scaffolding costs and meant that high safety standards could be implemented as early as the planning phase.

Joining forces for adaptability

At peak times, around 1, 300 t of PERI system material were in use at the same time on a daily basis. Standing scaffolds, safety scaffolds, suspended scaffolds, shoring, stairways, material platforms and mobile working scaffolds were all permanent fixtures on site.

In particular, the combination of the PERI UP scaffolding kit and system components from the VARIOKIT engineering construction kit ensured geometric and structural adaptability – and therefore the highest degree of occupational safety. The metric basic grid of both PERI systems allowed for flexible adaptation of the scaffolding solution using system components.

In addition to the extremely restrictive spatial conditions, the 30-m-high heavy-duty platforms designed for 20 kN/m² on the northern side of the building, which were used for bringing work materials and equipment into the building, were challenging in terms of the scaffolding technology employed. Most notably, the bridging construction with its tensioning system and its span of 12.75 m at a height of 33 m was another masterstroke by the planning and assembly team. Based on RCS climbing rails from the VARIOKIT engineering construction kit, it was possible to pre-assemble the bridge as a single unit on the ground and lift it into place with the mobile crane.

Seamlessly safe

In addition to the almost gap-free design of the PERI UP deck levels thanks to the geometric adjustment options in the 25 cm metric grid, trip-free corner designs and transitions involving system components also ensured that the scaffold could be used safely. Due to the flexibility of the components and the uniform metric grid, it is possible to work with system components without losing valuable time deploying special components and creating special-purpose solutions during planning and assembly/disassembly processes. The high safety standards were also reflected in numerous details: inward-opening safety swing gates were used when leaning ladders were required and scaffold nodes were encased in protective caps in a signal colour. These are representative of the smart supplementary components in the PERI UP scaffolding kit.

PERI GmbH
Formwork Scaffolding Engineering

Contact
Tanja Häuptle
Phone +49 (0) 7309 950 1173
Fax +49 (0) 7309 951 1173
segment.communication@peri.de

https://www.peri.com/en/company/press.html

Image 1
State-of-the-art, BIM-based scaffold planning and innovative PERI systems were instrumental in the construction of the new vitamin A complex at BASF SE in Ludwigshafen, Germany.
(Photo: PERI Germany)

Image 2
At peak times, up to 1, 300 t of PERI system material were in use on a daily basis.
(Photo: PERI Germany)

Image 3
The 30-m-high heavy-duty platforms and a bridging construction on the northern side of the building proved to be challenging aspects of the PERI scaffolding solution.
(Photo: PERI Germany)

Image 4
It was possible to combine PERI UP and VARIOKIT in an extremely versatile manner for a wide range of applications – for example, for forming the bridging construction with its tensioning system and its span of 12.75 m at a height of 33 m.
(Photo: PERI Germany)

Image 5
The metric basic grid of the PERI UP scaffolding kit ensured a high level of geometric and structural adaptability – and therefore a high degree of occupational safety.
(Photo: PERI Germany)

Image 6
The majority of the approximately 4, 000 scaffolding units were planned using CAD and provided as 3D models over the course of the 18-month project term required to construct the complex BASF plant. In this way, it was possible to minimise conversion times, optimise scaffolding costs and implement high safety standards as early as the planning phase.
(Photo: PERI Germany)

Image 7
Thanks to the geometric adjustment options in the 25 cm system grid, it was possible to implement a virtually gap-free design for the PERI UP deck levels.
(Photo: PERI Germany)

Image 8
Trip-free corner designs and transitions using PERI UP system components ensured that the scaffold could be used safely. Protective caps in a signal colour rounded off the safety concept. (Photo: PERI Germany)

Image 9
Where the modular ULS system formwork girder was used for bridging, the decks could be installed directly on the top chords, meaning the deck direction could be changed at any time.
(Photo: PERI Germany)

Scaffold construction project management
promaintain GmbH & Co. KG, Ingolstadt, Germany

Client
BASF SE, Ludwigshafen, Germany

Field service
PERI Competence Center Industrie, Weissenhorn; PERI branch office in Stuttgart
 
press contacts

Tanja Häuptle
Germany
Tel.:
+49 (0) 7309 950 1173
Fax:
+49 (0) 7309 951 1173
e-mail original [rar 1122 K]
technologies

© 2007