New headquarters for VakifBank

Press Release / November 2019

New headquarters for VakifBank

Shape of towers varies between rectangles and hexagons

With the new headquarters of VakifBank, Istanbul is now in the process of becoming a financial capital. Covering a total area of 690, 000 m² with 257, 464m² of usable area, the office construction will be one of the most spectacular buildings to be located in the Istanbul Finance Centre. Doka offered a suitable formwork solution for the special design of the two towers.

Acknowledged as one of the biggest state-owned banks in Turkey, VakifBank was established in 1954 and has since become an international institution with offices in New York, Bahrain and through participation in Vienna, Cologne and Frankfurt. Back in its home city of Istanbul the bank decided to build a brand new headquarters that drew on “Islamic patterns born out of mathematical wisdom, ” according to architects Tabanlıoğlu Mimarlık A.Ş, however, finding a formwork solution for this striking design wouldn’t come without its own set of challenges. This was one of the reasons why the engineering hours on the project exceeded 4500 hours.

Working with main contractor REC Rönesans Uluslararası İnşaat Ticaret A.Ş, both Doka Turkey and Doka’s high-rise engineering department were challenged to find a suitable formwork solution for the two business towers, which resulted in the team having to draw on their extensive experience and resources. Finding a suitable formwork solution for this project was extremely challenging. Firstly, the shape of the towers varied between rectangles and hexagons, which also varied from floor to floor. In addition, the design meant typical slabs were missing which complicated things even further. Furthermore; post- tensioning cables of slab and steel plates of facade application required special solutions for protection screen designs.

Covering a total area of 690, 000 m² with 257, 464m² of usable area, the towers will reach heights of 221.3 m and 151.6 m respectively upon completion, covering 52 and 36 storeys. Central to the brief was to provide maximum safety, which led to Doka using its Xclimb 60 Protection Screen. Thanks to its slab-to-slab coverage, site teams were not only protected from fall risk, but furthermore from Istanbul’s inclement winter weather.

Speaking on behalf of the contractor Sinan Sungur, site construction chief said, “Working with the Xclimb 60 Protection Screen not only provided the high levels of safety we were looking for, but furthermore allowed us to get on with the job in hand. Site teams work a lot more efficiently when they feel secure.”

With progress moving along, Doka Turkey was able to secure this project thanks to its tailored safety and sophisticated engineering solution, on site instruction and its ability to think on its feet. At the time of writing, the project will be handed over in August 2020.

In short:

Project: VakifBank Headquarters
Location: Istanbul, Turkey
Type of structure: High-rise, Office building
Height: 221.3 m & 151.6 m
Number of storeys: 52 & 36
Developer: VAKIF GYO
Main Contractor: REC Uluslararası İnşaat Yatırım Sanayi ve Ticaret A.Ş
Architect: Tabanlıoğlu Mimarlık A.Ş
Start of construction: 05/2017
Scheduled completion: 08/2020
Systems used: Doka Protection Screen Xclimb 60
Services: Engineering, Formwork instructor services

Photos:

Please include details of copyright for publication.

Covering a total area of 690, 000 m² with 257, 464m² of usable area, the towers will reach heights of 221.3 m and 151.6 m respectively upon completion, covering 52 and 36 storeys.
Photo: VakifBank_1.jpg
Copyright: Doka

Central to the brief was to provide maximum safety, which led to Doka using its Xclimb 60 Protection Screen.
Photo: Vakifbank_2.jpg
Copyright: Doka

About Doka:
Doka is a world leader in developing, manufacturing and distributing formwork technology for use in all fields of the construction sector. With more than 160 sales and logistics facilities in over 70 countries, Doka has a high-performing distribution network which ensures that equipment and technical support are provided swiftly and professionally. An enterprise forming part of the Umdasch Group, Doka employs a worldwide workforce of 7, 000.

Press contact
Doka
Michael Fuker