contacts
technologies

VARIOKIT tunnel formwork solution deep in the heart of the Golden City

VARIOKIT tunnel formwork solution deep in the heart of the Golden City

Chinatown Subway Station, San Francisco, USA

With construction work being carried out in depths up to 30 metres in the centre of the city famous for the Golden Gate Bridge, an enormous building structure is being realised. When completed, the Chinatown Subway Station will form the northern end of San Francisco's Central Subway System. The new station will significantly improve access to public transport in some of the city's most densely populated areas. The architectural requirements presented the contractor with enormous challenges. PERI developed a project-specific solution based on the VARIOKIT Engineering Construction Kit in order to economically construct the inner lining.

The highest point of the oval-shaped underground structure is still 17 m below Stockton Street which is why the construction using the cut-and cover method would have been too cumbersome and expensive. The contractor therefore decided in favour of shotcrete construction, also known as the New Austrian Tunnelling Method, in which excavation work takes place step-by-step from top to bottom. As more and more soft ground is excavated, temporary reinforcement provides support for the ever-increasing wall surface of the hollow space. Shotcrete applied to the surfaces supported the cavity until the inner lining could be cast in situ.

Project-specific VARIOKIT solution deep underground

The solution provided by PERI engineers for executing the enormous 60 m long Chinatown Station with a 15 m diameter stipulated concreting operations in 9 m sections. In order to be able to carry the large and heavy formwork ring, a project-specific formwork carriage consisting of high load-bearing VARIOKIT core components was realised. The pre-assembled formwork elements, comprised of GT 24 formwork girders and plywood formling, also saved weight when compared to using heavier steel formwork. These were lowered from Stockton Street through the site access to a depth of 30 metres and then mounted on the rail-guided VARIOKIT Tunnel Formwork Carriage. The hydraulic support of the VTC accelerated shuttering operations after the reinforcement had been placed in position. Concreting took place alternately on both sides in order to keep the supporting structure balanced. Vibrators mounted on the formwork could also be activated as required which ensured uniform compaction of the poured concrete.

Different cross-section – same supporting structure

Once the procedure had been established, the 9 m sections could then be concreted in five to six hours thanks to the high permissible fresh concrete pressure of up to 90 kN/m². After each concreting operation, striking was easily and quickly carried out by means of the hydraulic support. The tunnel formwork carriage was subsequently pulled along rails using heavy-duty wheels to the next section.

After the first ten concreting cycles, the tunnel profile changed. Due to the flexible VARIOKIT modular construction system complete with numerous rentable system components and the VTC Telescopic Prop, the supporting structure together with the other components were easily adapted in order to accommodate the new geometry. Once equipped with the new formwork elements, the final 10 sections could likewise be quickly realised thanks to the well-coordinated and practised procedures.

Individual formwork and logistics solution from a single source

The VARIOKIT modular construction kit is characterised by its great flexibility, high load-bearing capacity of its components and their low weight. The project-specific solution with prefabricated timber formwork panels delivered to the construction site as well as the large proportion of rentable system components provided the clients with enormous savings regarding investment, logistics and the amount of work involved. Due to the high adaptability of the system, numerous time-consuming and cost-intensive carpentry solutions could be dispensed with. Construction site support provided by the PERI project support team continuously optimised all work processes.

PERI GmbH
Formwork Scaffolding Engineering

Contact
Tanja Haeuptle
Phone +49(0)7309.950-1173
Fax +49(0)7309.951-173
Tanja.hauptle@peri.de

peri.com/press

Image 1
The project-specific solution for realising the inner lining was based on a moveable supporting structure consisting of system components taken from the VARIOKIT Engineering Construction Kit.
(Photo: PERI GmbH)

Image 2
The oval-shaped underground structure measures 15 metres in diameter and is up to 30 metres below the city centre of San Francisco.
(Photo: PERI GmbH)

Image 3
The high load-bearing capacity of the VARIOKIT system components facilitated the safe transfer of large loads while simultaneously allowing flexible adaptation to accommodate the challenging tunnel cross-section.
(Photo: PERI GmbH)

Image 4
In order to keep the supporting structure safely balanced, concreting was carried out alternately on both sides. Vibrators mounted on the formwork ensured uniform distribution of the concrete.
(Photo: PERI GmbH)

Image 5
When adapting to match the change in the cross-section, the patented Telescopic Posts could be quickly adjusted to the correct length in just a few easy steps.
(Photo: PERI GmbH)

Contractor
Tutor Perini Civil Sylmar, CA
Field Service
PERI Woodland
 
press contacts

Tanja Haeuptle
Germany
Tel.:
+49(0)7309.950-1173
Fax:
+49(0)7309.951-173
e-mail original [rar 1087 K]
technologies

© 2007