contacts
technologies

With PERI know-how and support for the best architectural concrete quality

With PERI know-how and support for the best architectural concrete quality

Hong Kong-Zhuhai-Macao Bridge / Tunnel Operation Buildings, Hong Kong, China

Since 2010, PERI has been supporting the construction of the 6 km long underwater tunnel section of the fixed link between Hong Kong and Macao / Zhuhai with the provision of two forming machines. The excellent cooperation has led to additional orders: PERI has provided professional engineering services and project specific formwork solutions for achieving the best possible architectural concrete results as well as large time savings during construction work for the tunnel portals and two operation buildings.

The mega project to create a 35 km long road between Hong Kong and the Chinese mainland started a few years ago in China. In the area of the approach flight path of the Hong Kong International Airport, Check Lap Kok, the connection runs through an underwater tunnel. PERI developed two hydraulically operated forming machines to produce the individual segments for this 6 km long tunnel which was finally completed in May 2017. The extremely positive, successful cooperation resulted in the China Communications Construction Company Ltd. (CCCC) commissioning the Weissenhorn based company to deliver additional engineering work and formwork material. Since the end of 2014, PERI has therefore been developing comprehensive formwork solutions for the tunnel entrances; just over a year later, the company received the order for supplying the formwork solutions for the operations buildings on two artificial islands in the Southern Chinese Pearl River Delta. For the customer, the most important requirement was to achieve a first class architectural concrete quality.

The structures

At the transition area leading down from the bridge, six lanes with a 3 % longitudinal gradient disappear into the tunnel whereby two artificial islands were created in order to accommodate these crossover points. For the transition structures, it was necessary to realize the up to 15.50 m high side walls of the entrances with a clearly structured joint and tie arrangement as well as ensuring they are permanently impermeable to water. In addition, enormous wave breakers were put in place around the islands.

Since autumn 2015, multi storey operation buildings have now been constructed on the two artificial islands which reach a size of almost 100, 000 m² for each respectively. In the structure at the west end of the tunnel – which has around 19, 000 m² of usable space – machine rooms, fire fighting equipment and office space will subsequently be accommodated; with one basement level and three above ground floors, this building is almost 20 m high. At the eastern exit of the tunnel, a 23.60 m high, 4 storey building has been realized. In addition to the service and equipment areas of the tunnel operator, two storeys with retail areas are also located here. Furthermore, an exhibition has been planned for the top floor which will feature the development and realization of this mega project.

The planning

As the Chinese client had had little experience with the construction of architectural concrete structures, defining the required fair faced concrete results was to be decided on at the start of the planning. The contractual partners selected Architectural Concrete Class SB 4 as the decisive quality feature in accordance with the Architectural Concrete Reference Guidelines published by the German DBV and VDZ associations. Subsequently, all project participants analysed any required adjustments to the usual construction methods that might be needed on the jobsite itself. The PERI experts drew up numerous suggestions for improvement in order to cost effectively and efficiently achieve the previously defined architectural concrete results.

The usual construction methods for different areas needed to be modified including, among other things, the intersections of main and secondary beams. On site, it is customary to concrete slabs and beams in one pour. By contrast, during the planning process it was decided to concrete all components separately and, in addition, use prefabricated reinforcement cages. The aim of these measures was to facilitate the efficient use of system formwork and to significantly accelerate the construction time.

After the realization of these foundations, planning the formwork and shoring required for the walls, columns, main and secondary beams, slabs, balconies and cantilevered parapets took place. As far as possible, the planning team used PERI system formwork in order to optimize the cost effectiveness of the construction work. Due to the in part curved shapes, PERI engineers also designed special formwork for numerous components.

The execution

The fabrication of the up to 15.50 m high reinforced concrete walls, which separate the two lanes in the area of the tunnel entrances, is carried out with mobile PERI portal formwork carriages. This movable solution includes a project specific VARIO GT 24 Girder Wall Formwork, which enabled the construction team to realize the required, clearly structured joint and tie arrangement for the walls. Moreover, the use of the SK Tie Technology provided the high degree of water tightness required throughout. Also for the massive breakwater, the construction team used a mobile PERI wall formwork solution.

For the large sized columns, slabs, cantilevered balconies and parapets, PERI developed formwork and scaffolding solutions based on standard components of various PERI systems. The Weissenhorn based company also planned, produced and supplied project specific solutions with timber formers and a range of cut to size plywood panels for the more complex shaped areas and components. All system components and panel cuts used were delivered to the construction site just in time and assembled on site according to the construction progress.

Through the combination of competent PERI engineering, efficient system formwork, precisely matching special formwork and continuous support along with quality control of all work carried out by a PERI supervisor, the contractor was able to achieve a reduction in the construction time of around 6 months compared to his primary planning.

The key to success
An important success factor for the expanded construction measures in the course of the gigantic HZMB project was the close and constructive cooperation between the Chinese construction company and PERI. The positive experience of both sides gained from the tunnel project could be used for the adjacent structures: the clients trusted the expertise and competence from Germany, and were open to suggestions for improvement and completely new methods. Completion of the structures on the islands is planned for October 2017. An interesting film about the construction site can be found on YouTube using this link: https://www.youtube.com/watch?v=cNXYhBY5nZw.

PERI GmbH
Formwork Scaffolding Engineering
Rudolf-Diesel-Strasse
89264 Weissenhorn
Germany
Phone +49(0)7309.950-0
Fax +49(0)7309.951-0

Contact
PERI Editorial Office
Phone +49(0)7309.950-1191
Fax +49(0)7309.951-1191

Image 1
On two artificial islands at both exits of the HZMB tunnel, striking architectural concrete structures are currently being built. On the right of the picture, the exit at the west end of the tunnel can be seen.
(Graphic: © China Communications Construction Company Ltd. CCCC)

Image 2
The directions of travel for the tunnel are separated by 15.50 m high reinforced concrete walls. Supported on the walls is a steel structure which serves as a sun shield. The multi storey building is being build in the lengthening of the tunnel entrance.
(Photo: PERI GmbH)

Image 3
With the PERI solution, the construction team achieved the best SB 4 architectural concrete quality with a clearly structured joint and tie arrangement as well as permanent water impermeability for the walls of the tunnel entrance.
(Photo: PERI GmbH)

Image 4
PERI also planned and delivered the formwork solutions for the circumferential wave breakers as well as the multi-storey operation buildings on the artificial islands. The highest possible architectural concrete quality was the decisive requirement for the execution of the construction work.
(Photo: PERI GmbH)

Image 5
The PERI formwork solution for the slabs, cantilevered balconies and parapets is largely based on standard components taken from various PERI systems. The Weissenhorn based company also planned, produced and delivered countless timber formers and other cut to size plywood panels for the circular shaped areas.
(Photo: PERI GmbH)

Image 6
During the planning work, the project partners decided to change the previously agreed construction method. Among other things, beams and slabs were to be concreted separately. Result: system formwork could be used efficiently and the previously planned construction period reduced by 6 months.
(Photo: PERI GmbH)

Image 7
The cut-to-size plywood formlining for the project-specific formwork of the large-sized columns was planned and produced in Weissenhorn.
(Photo: PERI GmbH)

Image 8
For the construction team, execution of such high architectural concrete quality was an entirely new experience. Two PERI supervisors therefore supported the project managers on site during the entire construction period ensuring constant quality assurance.
(Photo: PERI GmbH)

Contractor
China Communications Construction Company Ltd. (CCCC), China

Field Service
PERI Asia Pacific and PERI Weissenhorn, Germany

Re-printing of this article is free of charge but with reference to PERI GmbH as the source
Copy kindly requested
Number of characters: 8031
 
press contacts

Germany
Tel.:
+49(0)7309.950-1191
Fax:
+49(0)7309.951-1191 original [rar 1061 K]
technologies

© 2007