Largest offshore facility ever built in Baku sails away

AMEC, the international engineering and project management company, and its partners in the AMEC-Tekfen-Azfen (ATA) consortium, celebrated the successful completion and sail-away of the latest Chirag Oil Project topsides for Azerbaijan International Oil Company (AIOC).

The Chirag Oil Project – West Chirag (COP-WC) topsides is the largest facility ever built in Baku with a load-out weight of 20,000 tonnes. The COP-WC platform is the fourth phase of the Azeri-Chirag-Gunashli (ACG) development operated by BP on behalf of AIOC in the Azerbaijan sector of the Caspian Sea.

The single integrated deck consists of a 48-slot drilling, processing and 175 bed-living quarters platform. The latest facility will be connected via the new subsea pipelines into the existing ACG infrastructure and will be used to enhance oil production and recovery by drilling more wells.

"Construction on the project commenced in July 2010 after some six months upgrade and expansion of the ATA yard. This followed the successful completion of both the Process, Compression, Water Injection and Utilities (PCWU) and the Compression and Water Injection topsides for the Central Azeri field, " said AMEC's in-country manager Peter Ward.

"At peak we had over 3,000 people working at the yard who, I am proud to say, achieved 19 million man-hours without a single lost time incident on the project. A genuinely world class performance."

The yard upgrade included the opening of an onsite welder training school, which was used to assess, coach and test over 1,000 welders. A separate training facility was also set up to train and develop the electrical trades to ensure that the quality of the installation was of the highest standard.