Amec awarded FEED for Gateway project

UK-based construction group Amec along with Parsons Brinckerhoff and Senergy, has been appointed by Gateway Storage Company to undertake the front-end engineering design (FEED) for both the offshore and onshore elements of the £600 million Gateway offshore underground gas storage scheme.

The Gateway storage scheme will be located in the East Irish Sea, approximately 25 kilometres (15 miles) offshore, south west of Barrow-in-Furness. The current phase of the project will provide 1.5 billion cubic metres of storage capacity, with the possibility of expansion in the future.

The work over the next 12 months will support a commitment to construction of the facility at the end of 2010 and enable the commencement of gas storage services for the UK market in 2014.